Category Archives: Project

Featured Video Play Icon

Miami Herald Media Company – HQ Relocation

Location: Miami Herald Media Company, 3511 NW 91st Court, Doral, Florida

Owner: Miami Herald Media Corporation

Architect: Dario Designs, Inc.

Interior Designer: GAlvarez Studio, Inc.

Construction Manager: Link Construction Group, Inc.

Duration: 14 months

Project Description: The renovation of an existing two (2) story, 159,000 SF office building to accommodate over 650 employees.

Role: Construction Management and Furniture, Technology and Move procurement and coordination.

DLA, Inc.

Location: Federal Reserve Bank – 9100 N.W. 36th Street, Doral, Florida

Tenant: DLA, Inc.

Architect: G.Alvarez Studio, Inc.

Construction Manager: Charland Rurey Construction, Inc.

Duration: 10 months

Project Description: 35,000 SF

Role: Construction Management, furniture, audio visual, security, server room and structured cabling coordination.

Paul Mitchell the School – Miami

Location: 8905 Dadeland Blvd., Miami, Florida

Tenant: Paul Mitchell the School

Architect: Powell, Dudley, Frith Architects

Construction Manager: MW Mitchell Construction & Development

Duration: 7 months

Project Description: 10,000 SF

Role: Construction Management and Furniture, Audio Visual, Security, Structured Cabling System and Move procurement and coordination.

Baptist Health South Florida

Location: 9001 N.W. 33rd Street, Doral, Florida

Owner: Baptist Health South Florida

Design/Builder: Aligned Properties, Inc.

Architect: RLC Architects, P.A.

Construction Manager: Link Construction Group, Inc.

Duration: 16 months

Project Description: Ground–up construction of a one (1) story, 159,000 SF centralized distribution center on approximately six (6) acres including: 15,000 SF of office space and 20,000 SF of conditioned storage space. The facility will be the home of the fifty five (55) person Supply Chain Group serving South Florida.

Role: Design/Builder Representative

Featured Video Play Icon

50 Milk Street Redevelopment

Location: 50 Milk Street, Boston, Massachusetts

Owner: Ponte Gadea Boston, LLC

Architect (Lobby / Façade): Perkins + Will

Architect (Interiors): Dyer Brown & Associates

Construction Manager: Lee Kennedy & Company

Duration: 12 months

Project Description: The redevelopment of twenty one (21) story Class A office building with a total of 295,000 RSF; including base building mechanical system re-design and upgrades, lobby and façade re-design and renovation, design and construction of conference center and exercise facility.

Role: Construction Management, Lease Negotiation and Landlord Work (Tenant Improvements)

Millicom International Services, LLC HQ Expansion & Relocation

Location: 396 Alhambra Circle, Coral Gables, Florida

Tenant: Millicom International Services, LLC (Tigo)

Architect: G.Alvarez Studio, Inc.

Construction Manager: City Construction Group, Inc.

Duration: 8 months

Project Description: 22,000 SF interior renovation.

Role: Construction Management and Furniture, Audio Visual, Security, Structured Cabling System and Move procurement and coordination.

The Palms at Town & Country

Location: Northwest corner of Kendall Drive and S.W. 117th Avenue, Miami, Florida

Owner: TIAA-CREF

Architect: Robin Bosco Architects & Planners, Inc.

Construction Manager (Site Improvements/Convienence Ctr.): Flagler Construction Group, Inc.

Construction Manager (Retail): Brasfield & Gorrie, Inc.

Duration: 48 months

Project Description: Redevelopment of 700,000 SF life style center and convenience center. Included the following tenants:

  • 24 Hour Fitness
  • Nordstrom Rack
  • Kohl’s
  • Loehmann’s
  • Loehmann’s Mens
  • Total Wine & Spirits
  • Dick’s Sporting Goods
  • Blue Martini
  • Cadillac Grill
  • Carmine’s Trattoria
  • Hagaan Daz

Role: Development Manager

Miami Herald Media Company – Production Facility Relocation

Location: 3500 N.W. 89th Court, Doral, Florida

Owner: Miami Herald Media Company

Architect: Dario Designs, Inc.

Interior Designer: GAlvarez Studio, Inc.

Construction Manager: Link Construction Group, Inc.

Duration: 24 months

Project Description: Ground-up construction of a three (3) story, 120,000 SF commercial printing production building, including site improvements for an eight (8) acre parcel.

Role: Construction and Development Management and Technology, Equipment, Printing Press and Move Procurement and Coordination.

Lilt Lounge

Location: Epic Hotel, Miami, Florida

Owner: Epic Hotel, LLC

Architect: Virtual Design & Consulting Inc.

Interior Designer: Puccini Group

Construction Manager: City Construction Group, Inc.

Duration: 5 months

Project Description: 3,500 SF

Role: Construction Management and furniture, kitchen equipment and audio visual coordination.